PMI-SP · Question #16
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #16. The question stem and answer options stay visible for context.
Schedule Monitoring and Controlling
Question
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
Exhibit
Options
- AZero
- BOne
- CFour
- DFive
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#float calculation#network diagram#activity delays#critical path