nerdexam
PMI

PMI-SP · Question #9

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #9. The question stem and answer options stay visible for context.

Schedule Monitoring and Controlling

Question

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?

Options

  • A1.02
  • B0.010
  • C0.75
  • D0.95

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#TCPI#to-complete performance index#earned value#BAC
Full PMI-SP Practice