PMI-SP · Question #9
PMI-SP Question #9: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #9. The question stem and answer options stay visible for context.
Question
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?
Options
- A1.02
- B0.010
- C0.75
- D0.95
Unlock PMI-SP to see the answer