PMI-SP · Question #10
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project…
The correct answer is A. Schedule compression. Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and…
Question
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?
Options
- ASchedule compression
- BReserve analysis
- CVariance analysis
- DExpert judgment
How the community answered
(53 responses)- A92% (49)
- B4% (2)
- C2% (1)
- D2% (1)
Explanation
Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and lags Schedule compression Answer options D, B, and C are incorrect. These are not tools and techniques for schedule
Topics
Community Discussion
No community discussion yet for this question.