nerdexam
PMI

PMI-SP · Question #10

Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project…

The correct answer is A. Schedule compression. Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and…

Schedule Planning and Development

Question

Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?

Options

  • ASchedule compression
  • BReserve analysis
  • CVariance analysis
  • DExpert judgment

How the community answered

(53 responses)
  • A
    92% (49)
  • B
    4% (2)
  • C
    2% (1)
  • D
    2% (1)

Explanation

Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and lags Schedule compression Answer options D, B, and C are incorrect. These are not tools and techniques for schedule

Topics

#schedule development#schedule compression#tools and techniques#PMI process