nerdexam
PMI

PMI-SP · Question #46

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time…

The correct answer is C. Control schedule. In severe cases, new schedule duration estimates with new forecasted start and finish dates are needed. In these instances, it is an example of using the control schedule process. Control schedule process is a method of monitoring the status of the project to update project…

Schedule Monitoring and Controlling

Question

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

Options

  • AEstimate activity durations
  • BEstimate activity resources
  • CControl schedule
  • DDevelop schedule

How the community answered

(23 responses)
  • A
    4% (1)
  • C
    87% (20)
  • D
    9% (2)

Explanation

In severe cases, new schedule duration estimates with new forecasted start and finish dates are needed. In these instances, it is an example of using the control schedule process. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule baseline. It is concerned with: Determining the current status of the project Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Control schedule is a component of the Perform Integration Change Control process. Answer option B is incorrect. The activity resources would only address the addition or replacement of resources needed to complete the project work. Answer option A is incorrect. This is a tempting choice, but according to the PMBOK, new schedules are part of the control schedule process. Answer option D is incorrect. Develop schedule is not the best choice for this question. It is a process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

Topics

#control schedule#schedule baseline#corrective action#target schedule

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice