Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is…

The correct answer is B. Managing the day-to-day events of a project. Apportioned effort is effort applied that you cannot subdivide into work packages, but it is related to, usually in a supportive role, to the completion of the project work packages. The project management overhead, such managing the project work, is an example of apportioned…

Schedule Planning and Development

Question

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

Options

  • AAdding features to the project's product that is not included in the project scope.
  • BManaging the day-to-day events of a project.
  • CCreating software as defined in the project scope.
  • DCompleting project activities as start-to-start events.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    96% (25)

Explanation

Apportioned effort is effort applied that you cannot subdivide into work packages, but it is related to, usually in a supportive role, to the completion of the project work packages. The project management overhead, such managing the project work, is an example of apportioned effort. Apportioned effort (AE) is the effort that is applied to the project-related work that cannot be easily and readily divided into discrete efforts for those tasks, but which is associated in a direct proportion to the discrete work efforts that are capable of being measured. The presence of apportioned effort relies particularly on the performance of further efforts. Answer option C is incorrect. This is an example of discrete effort. Answer option A is incorrect. This is an example of a scope change that has not been approved. Answer option D is incorrect. This is an example of a scheduling technique.

Topics

#apportioned effort#activity types#activity list#work categorization