You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #44. The question stem and answer options stay visible for context.

Schedule Planning and Development

Question

You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

Options

  • AWednesday
  • BThursday
  • CMonday
  • DTuesday

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#schedule calculation#working days#project calendar#duration arithmetic