PMI-SP · Question #25

PMI-SP Question #25: Real Exam Question with Answer & Explanation

The correct answer is C. Resource-oriented scheduling. Resource-oriented scheduling focuses on using and scheduling particular resources in an effective manner. This type of scheduling should be used whenever there are limited resources available for a project and the struggle for these resources between the project activities is int

Question

You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

Options

  • ACritical path scheduling
  • BTime-oriented scheduling
  • CResource-oriented scheduling
  • DNetwork scheduling

Explanation

Resource-oriented scheduling focuses on using and scheduling particular resources in an effective manner. This type of scheduling should be used whenever there are limited resources available for a project and the struggle for these resources between the project activities is intense. As a result, delays are likely to arise in such cases, as actions must wait until general resources become available. Resource-oriented scheduling is also suitable in cases where unique resources are to be used, such as when there is only one excavator available in an excavation operation. Answer option B is incorrect. Time-oriented scheduling is a time-scheduling method that focuses on determining the finishing time of a project. It also specifies the crucial precedence relationships among the activities involved in the project. In time-oriented scheduling, the appropriate time is allocated for the whole project through the successive stages of the project life cycle. Answer option A is incorrect. Critical path scheduling is a technique that calculates the minimum completion time for a project along with the possible start and finish times for the project activities. Answer option D is incorrect. Network scheduling provides a basis for obtaining facts for decision making.