PMI-SP · Question #24

Michelle works as a scheduler in Array Inc. She has to create a schedule for a project assigned to her. Choose and reorder the steps that she should follow while creating the schedule for the project.

The correct answer is C. Resource-oriented scheduling. You've hit your limit · resets 5:20am (America/New_York)

Schedule Planning and Development

Question

Michelle works as a scheduler in Array Inc. She has to create a schedule for a project assigned to her. Choose and reorder the steps that she should follow while creating the schedule for the project. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to move the item back to the right pane. Click and buttons to sort the list, if required. Answer:

Exhibits

PMI-SP question #24 exhibit 1
PMI-SP question #24 exhibit 2

Options

  • ACritical path scheduling
  • BTime-oriented scheduling
  • CResource-oriented scheduling
  • DNetwork scheduling

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    75% (18)
  • D
    13% (3)

Explanation

You've hit your limit · resets 5:20am (America/New_York)

Topics

#schedule development process#scheduling steps#WBS#schedule creation