PMI-SP · Question #12

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: You are concerned about a risk on Activity G that if it happens will delay the…

The correct answer is D. Zero. There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint…

Schedule Monitoring and Controlling

Question

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

Exhibit

PMI-SP question #12 exhibit

Options

  • AFive days
  • BFour days
  • CEleven days
  • DZero

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    20% (5)
  • C
    24% (6)
  • D
    48% (12)

Explanation

There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.

Topics

#float analysis#network diagram#critical path#risk offset