PMI
PMI-SP · Question #37
Risk event is the description of what may happen to the _____ of the project.
The correct answer is B. harm. You've hit your limit · resets 5am (America/New_York)
Schedule Monitoring and Controlling
Question
Risk event is the description of what may happen to the _____ of the project.
Options
- ABudget
- Bharm
- CSchedule
- DManager
How the community answered
(44 responses)- A2% (1)
- B86% (38)
- C5% (2)
- D7% (3)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#risk event#risk definition#schedule risk#risk management