nerdexam
PMI

PMI-SP · Question #32

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,1

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #32. The question stem and answer options stay visible for context.

Schedule Monitoring and Controlling

Question

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

Options

  • A$122,845
  • B-$51,000
  • C-$85,000
  • DZero

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#cost variance#earned value management#CV calculation#crashing impact
Full PMI-SP Practice