nerdexam
PMI

PMI-SP · Question #39

On what is project baseline development established?

The correct answer is B. Estimated project cost and schedule. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

On what is project baseline development established?

Options

  • AApproved product requirements
  • BEstimated project cost and schedule
  • CActual project cost and schedule
  • DRevised project cost and schedule

How the community answered

(42 responses)
  • A
    7% (3)
  • B
    88% (37)
  • C
    2% (1)
  • D
    2% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#project baseline#baseline development#cost and schedule estimates#baseline establishment

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice