PMI-SP · Question #39
On what is project baseline development established?
The correct answer is B. Estimated project cost and schedule. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
On what is project baseline development established?
Options
- AApproved product requirements
- BEstimated project cost and schedule
- CActual project cost and schedule
- DRevised project cost and schedule
How the community answered
(42 responses)- A7% (3)
- B88% (37)
- C2% (1)
- D2% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#project baseline#baseline development#cost and schedule estimates#baseline establishment