PMI-SP · Question #50
You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the…
The correct answer is B. Schedule data. Schedule data is an output of the Develop Schedule process. The nine inputs to the Develop Schedule process are: activity list, activity attributes, project schedule network diagrams, activity resource requirements, resource calendars, activity duration estimates, project scope…
Question
You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?
Options
- AResource calendars
- BSchedule data
- CActivity list
- DProject scope statement
How the community answered
(52 responses)- A4% (2)
- B87% (45)
- C8% (4)
- D2% (1)
Explanation
Schedule data is an output of the Develop Schedule process. The nine inputs to the Develop Schedule process are: activity list, activity attributes, project schedule network diagrams, activity resource requirements, resource calendars, activity duration estimates, project scope statement, enterprise environmental factors, and organizational process assets. Answer options C, A, and D are incorrect. These are the inputs to the Develop Schedule process.