What is the term assigned to graphic in the figure given below?

The correct answer is A. Communications bull's eye. The graphic shown in the figure is a communications bull's eye. The project manager must keep the project within the boundaries defined by the bull's eye or he will need to generate a performance report. This is an example of management by exception because the project manager…

Stakeholder Communication

Question

What is the term assigned to graphic in the figure given below?

Options

  • ACommunications bull's eye
  • BPerformance goals
  • CEarned value management goals
  • DProject exception report

How the community answered

(27 responses)
  • A
    93% (25)
  • B
    4% (1)
  • D
    4% (1)

Explanation

The graphic shown in the figure is a communications bull's eye. The project manager must keep the project within the boundaries defined by the bull's eye or he will need to generate a performance report. This is an example of management by exception because the project manager only communicates with management when there is an exception, or variance, within Answer options C, B, and D are incorrect. These are not valid terms for the communications bull's