You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?
Exhibit
Options
- AYour project's critical path will shift to ACFI.
- BYour project will be late by five days.
- CYour project can still complete on time as float is available onActivity I.
- DYour project will now have two critical paths.