PMI-SP · Question #18
You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete…
The correct answer is B. Your project will be late by five days. Activity F is on the critical path of ACFHK of 30 days. By adding five additional days to Activity F, the project will now take 35 days to complete. Answer options C, A, and D are incorrect. These are not the valid answers.
Question
You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?
Exhibit
Options
- AYour project's critical path will shift to ACFI.
- BYour project will be late by five days.
- CYour project can still complete on time as float is available onActivity I.
- DYour project will now have two critical paths.
How the community answered
(46 responses)- A4% (2)
- B65% (30)
- C20% (9)
- D11% (5)
Explanation
Activity F is on the critical path of ACFHK of 30 days. By adding five additional days to Activity F, the project will now take 35 days to complete. Answer options C, A, and D are incorrect. These are not the valid answers.
Topics
Community Discussion
No community discussion yet for this question.
