nerdexam
PMI

PMI-SP · Question #18

PMI-SP Question #18: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #18. The question stem and answer options stay visible for context.

Question

You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?

Exhibit

PMI-SP question #18 exhibit

Options

  • AYour project's critical path will shift to ACFI.
  • BYour project will be late by five days.
  • CYour project can still complete on time as float is available onActivity I.
  • DYour project will now have two critical paths.

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice