PMI-SP · Question #91
PMI-SP Question #91: Real Exam Question with Answer & Explanation
The correct answer is B. Create parametric estimates for repetitive activities.. Parametric estimates are created for repetitive tasks, such as four hours per unit installed; 1,000 units to install would equate to 4,000 hours. A template does not address this type of time estimating directly. A template for time estimating is an analogous estimate type. A tem
Question
Options
- AIdentify typical schedule milestones.
- BCreate parametric estimates for repetitive activities.
- CSave time creating activity duration estimates.
- DImport activity attributes.
Explanation
Parametric estimates are created for repetitive tasks, such as four hours per unit installed; 1,000 units to install would equate to 4,000 hours. A template does not address this type of time estimating directly. A template for time estimating is an analogous estimate type. A template for any project is an activity list or a part of the activity list from a previous project. The template contains the activity attributes information and other vivid information that are helpful to define activities. It is also used to classify schedule milestones. Answer option D is incorrect. Templates can include activity attribute information. Answer option A is incorrect. Templates do indicate milestones. Answer option C is incorrect. Templates can save time for the project manager and the project team.
Community Discussion
No community discussion yet for this question.