nerdexam
PMI

PMI-SP · Question #91

PMI-SP Question #91: Real Exam Question with Answer & Explanation

The correct answer is B. Create parametric estimates for repetitive activities.. Parametric estimates are created for repetitive tasks, such as four hours per unit installed; 1,000 units to install would equate to 4,000 hours. A template does not address this type of time estimating directly. A template for time estimating is an analogous estimate type. A tem

Question

You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?

Options

  • AIdentify typical schedule milestones.
  • BCreate parametric estimates for repetitive activities.
  • CSave time creating activity duration estimates.
  • DImport activity attributes.

Explanation

Parametric estimates are created for repetitive tasks, such as four hours per unit installed; 1,000 units to install would equate to 4,000 hours. A template does not address this type of time estimating directly. A template for time estimating is an analogous estimate type. A template for any project is an activity list or a part of the activity list from a previous project. The template contains the activity attributes information and other vivid information that are helpful to define activities. It is also used to classify schedule milestones. Answer option D is incorrect. Templates can include activity attribute information. Answer option A is incorrect. Templates do indicate milestones. Answer option C is incorrect. Templates can save time for the project manager and the project team.

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice