PMI-SP · Question #63
PMI-SP Question #63: Real Exam Question with Answer & Explanation
The correct answer is D. $23,750. Contingency reserves are estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events. These events are "known unknowns" and are part of the project scope and cost baselines. The contingency reserve is calculated by multipl
Question
Options
- A$142,000
- B$232,000
- C$41,750
- D$23,750
Explanation
Contingency reserves are estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events. These events are "known unknowns" and are part of the project scope and cost baselines. The contingency reserve is calculated by multiplying the probability and the impact for the risk event value for each risk event. The sum of the risk events equals the contingency reserve for the project. Note that Risk D is a positive risk amount. Answer option C is incorrect. This value is the sum of the risk events if you did not include Risk D as a positive risk value. Answer option A is incorrect. This is a sum of the risk event. Answer option B is incorrect. This is a sum of the risk events without including Risk D as a positive risk event.
Community Discussion
No community discussion yet for this question.