PMI-SP · Question #70
Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?
The correct answer is D. EV/PV. The schedule performance index is earned value divided by planned value. The close the result is to 1, the better the project is performing. Answer option B is incorrect. This is the cost variance formula. Answer option C is incorrect. This is the formula to find schedule…
Question
Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?
Options
- APV/EV
- BEV-AC
- CEV-PV
- DEV/PV
How the community answered
(43 responses)- B2% (1)
- C2% (1)
- D95% (41)
Explanation
The schedule performance index is earned value divided by planned value. The close the result is to 1, the better the project is performing. Answer option B is incorrect. This is the cost variance formula. Answer option C is incorrect. This is the formula to find schedule variance. Answer option A is incorrect. This is not a valid formula.
Topics
Community Discussion
No community discussion yet for this question.