PMI-SP · Question #69

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your…

The correct answer is A. Project calendar. The project calendar defines the working hours for the project, including any days that project work will not happen due to the organizational calendar. Answer option D is incorrect. The company calendar is not the correct choice for this question. Answer option C is incorrect…

Schedule Planning and Development

Question

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

Options

  • AProject calendar
  • BResource calendar
  • COrganizational calendar
  • DCompany calendar

How the community answered

(31 responses)
  • A
    94% (29)
  • B
    3% (1)
  • D
    3% (1)

Explanation

The project calendar defines the working hours for the project, including any days that project work will not happen due to the organizational calendar. Answer option D is incorrect. The company calendar is not the correct choice for this question. Answer option C is incorrect. The organizational calendar is not the correct choice for this Answer option B is incorrect. The resource calendar defines whether resources the project needs will be available. The resources include people, facilities, equipment, and other things that project needs to be completed.

Topics

#project calendar#resource calendar#organizational calendar#schedule planning