Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition…

The correct answer is C. Project communication management. Tom is working with the project communication management process, as it is required to ensure the timely disposition of project information. Project Communications Management is one of the nine Knowledge Areas. It employs the processes required to ensure timely and appropriate…

Stakeholder Communication

Question

Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

Options

  • AWork performance measurement
  • BStakeholder expectation management
  • CProject communication management
  • DStakeholder analysis

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    94% (31)

Explanation

Tom is working with the project communication management process, as it is required to ensure the timely disposition of project information. Project Communications Management is one of the nine Knowledge Areas. It employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information. The following processes are part of Project Communications Management: Identify Stakeholders Plan Communications Distribute information Manage Stakeholder Expectations Report Performance The Project Communications Management processes provide the critical links among people and information that are necessary for successful communications. These processes interact with each other and with the processes in the other Knowledge Areas as well. Answer option B is incorrect. Managing stakeholder expectation is the process of working and communicating with the stakeholders to meet their requirements. Answer option A is incorrect. Work performance measurement uses the information to create project activity metrics to evaluate actual progress compared to planned progress. Answer option D is incorrect. Stakeholder analysis is the process of gathering and analyzing quantitative and qualitative information to determine the interest of the stakeholders. You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

Topics

#communications management#information distribution#information management#project communications