You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project…

The correct answer is C. Precedence diagramming method. The precedence diagramming method is not a tool and technique that will be used during the activity definition process. Precedence diagramming method (PDM) is used in critical path methodology for building a project schedule network diagram that uses boxes or rectangles…

Schedule Planning and Development

Question

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Options

  • ADecomposition
  • BRolling wave plan
  • CPrecedence diagramming method
  • DTemplates

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    7% (3)
  • C
    89% (41)
  • D
    2% (1)

Explanation

The precedence diagramming method is not a tool and technique that will be used during the activity definition process. Precedence diagramming method (PDM) is used in critical path methodology for building a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities, and join each other with arrows that show the logical relationship that exists between them. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project. Expert The skilled members in a project team or other experts who develop project scope statements can help provide knowledge in defining activities.

Topics

#activity definition#decomposition#rolling wave planning#tools and techniques