You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will…

The correct answer is D. Earned value management results. The results of earned value management are not an input to the control schedule process. The fourth input is organizational process assets. The inputs of schedule control process are as Project Management Plan Project Schedule Work Performance Integration Organizational Process…

Schedule Monitoring and Controlling

Question

You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?

Options

  • AProject schedule
  • BWork performance information
  • CProject management plan
  • DEarned value management results

How the community answered

(36 responses)
  • A
    3% (1)
  • C
    6% (2)
  • D
    92% (33)

Explanation

The results of earned value management are not an input to the control schedule process. The fourth input is organizational process assets. The inputs of schedule control process are as Project Management Plan Project Schedule Work Performance Integration Organizational Process Assets Answer option C is incorrect. The project management plan is an input to the control schedule Answer option A is incorrect. The project schedule is an input to the control schedule process. Answer option B is incorrect. The work performance information is an input to the control schedule process.

Topics

#control schedule#process inputs#work performance information#project management plan