PMI-SP · Question #83
You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?
The correct answer is D. Templates. Templates are used to identify the typical schedule milestones in the Define Activity process. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient…
Question
You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?
Options
- AExpert Judgment
- BDecomposition
- CRolling Wave Planning
- DTemplates
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C3% (1)
- D89% (31)
Explanation
Templates are used to identify the typical schedule milestones in the Define Activity process. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project. Expert Judgement: The skilled members in a project team or other experts who develop project scope statements can help provide knowledge in defining