PMI-SP · Question #154
Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not…
The correct answer is A. Crash the project. The change in the amount of labor Ned is allowed to use will cause his project schedule to increase thereby affecting the project end date. Crashing the project will allow Ned to add more resources while still keeping each resource to a maximum of 25 hours per week. Answer…
Question
Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?
Options
- ACrash the project.
- BAdd more risk mitigation.
- CReduce the amount of labor.
- DReduce the project scope.
How the community answered
(52 responses)- A71% (37)
- B6% (3)
- C8% (4)
- D15% (8)
Explanation
The change in the amount of labor Ned is allowed to use will cause his project schedule to increase thereby affecting the project end date. Crashing the project will allow Ned to add more resources while still keeping each resource to a maximum of 25 hours per week. Answer option D is incorrect. Ned likely does not have control over descoping decisions. Answer option C is incorrect. Reducing the project labor is what resource leveling does. Answer option B is incorrect. Adding risk mitigation won't necessarily help Ned finish the project faster.