- Question #1Project Management Concepts
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project...
Change ManagementProject CommunicationProject Plan UpdateChange Control Process - Question #3Project Management Concepts
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?
Project Risk ManagementRisk Response StrategiesOpportunitiesExploit - Question #4Basics of IT and governance
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the followin...
Multitier ArchitectureEnterprise SolutionsClient-Server ArchitectureTechnical Requirements - Question #5Project Life Cycle Phases
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Choose two.)
Project initiationProject manager responsibilitiesProject objectivesResource assessment - Question #6Project Management Concepts
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evalua...
Project prioritizationStrategic alignmentOrganizational strategyVision and mission - Question #7Tools and documentation
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
Gantt chartProject schedulingSchedule managementProgress tracking - Question #8Tools and documentation
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
Task boardsAgile methodologiesProgress trackingStand-up meetings - Question #9Project Management Concepts
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to...
Cultural differencesGlobal teamsProject communicationStakeholder management - Question #10Project Management Concepts
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following: Which of the fol...
Root cause analysisIssue managementProblem-solvingProject troubleshooting - Question #11Basics of IT and governance
Which of the following describes three-tier architecture?
Three-tier architectureSystem architectureApplication layers - Question #12Project Management Concepts
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
Change Management ProcessRollback PlanningOperational ChangesRisk Mitigation - Question #13Basics of IT and governance
Which of the following offers administrators more direct control over operating systems?
Cloud computingCloud service modelsIaaSOS control - Question #14Basics of IT and governance
Which of the following items must be protected as PII? (Choose two.)
PIIData privacyInformation security - Question #15Project Management Concepts
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasi...
User adoptionChange managementPost-implementation supportTraining - Question #16Tools and documentation
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis: Based on the chart, which of the foll...
Burn Up ChartProject Status ReportingSchedule ManagementCost Management - Question #17Project Management Concepts
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Agile MethodologyProject Selection CriteriaUndefined RequirementsProject Characteristics - Question #18Tools and documentation
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the docum...
Statement of WorkSOWProject documentationProject planning - Question #19Project Management Concepts
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-...
PMO functionsOrganizational supportLessons learnedProject issue resolution - Question #20Project Management Concepts
A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the follo...
Resource managementResource allocationOver-allocationProject closure - Question #21Project Management Concepts
Which of the following requires the MOST availability from the business team?
Project Management MethodologiesAgileScrumStakeholder Engagement - Question #22Tools and documentation
Which of the following software programs would be BEST to use to store information related to business transactions?
Record Management SystemBusiness TransactionsInformation SystemsSoftware Applications - Question #23Project Management Concepts
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely b...
Project schedulingDependency managementIssue managementSchedule change management - Question #24Project Management Concepts
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
Project ProcurementStatement of Work (SOW)Procurement PlanningProject Documents - Question #25Project Management Concepts
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step f...
Task managementTeam communicationWork assignmentProject planning - Question #26Project Management Concepts
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
Project ManagementIssue ManagementImpact AssessmentProject Delays - Question #27Project Life Cycle Phases
Which of the following BEST identifies the intent and purpose of a project closeout report?
Project closeout reportProject closureProject completionProject life cycle phases - Question #28Project Management Concepts
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this...
ROIFinancial analysisProject initiationCost-benefit analysis - Question #29Tools and documentation
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)
Issue ManagementChange ManagementProject DocumentationProject Logs - Question #30Tools and documentation
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementati...
SOWContract ManagementScope DefinitionProcurement Documentation - Question #31Project Life Cycle Phases
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
Project InitiationProject CharterProject Manager ResponsibilitiesProject Phases - Question #32Project Management Concepts
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST...
Scope creepProject scopeRequirements management - Question #33Tools and documentation
Which of the following BEST illustrates how team members with different roles should interact on the team?
RACI matrixTeam rolesResponsibility assignmentProject communication - Question #34Tools and documentation
For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
RACI chartRoles and responsibilitiesProject planning toolsProject documentation - Question #35Tools and documentation
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use t...
Project Quality ManagementRoot Cause AnalysisIshikawa DiagramProblem Solving Tools - Question #36Tools and documentation
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use...
Project dashboardsProgress reportingStakeholder communicationCommunication tools - Question #37Project Management Concepts
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
MilestonesProject schedulingSchedule activitiesProject management terms - Question #38Project Management Concepts
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mob...
Change ManagementScope ManagementStakeholder Management - Question #39Project Management Concepts
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product...
Contingency PlanningRisk ManagementProject Planning - Question #40Project Management Concepts
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. W...
Quality assurance planningProject scope alignmentProject goalsProject management plans - Question #41Tools and documentation
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
Communication issuesCommunication planStakeholder communicationIssue resolution - Question #42Basics of IT and governance
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the foll...
Access ControlInformation SecuritySystem SecurityCompliance - Question #43Tools and documentation
An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions w...
Electronic Document ManagementRecord Management SystemsSoftware SolutionsBusiness Applications - Question #44Project Life Cycle Phases
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Project ClosureScope ValidationDeliverable AcceptanceProject Management Process - Question #45Project Life Cycle Phases
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
Regression testingSoftware testingQuality assuranceSystem maintenance - Question #47Project Life Cycle Phases
Which of the following project phases would include a feasibility study?
Project phasesFeasibility studyInitiating phaseProject life cycle - Question #48Project Management Concepts
Which of the following BEST describes a subject matter expert who is solicited for input during the development of a product?
Project RolesSubject Matter ExpertProduct Development - Question #49Project Management Concepts
When a project milestone is completed, which of the following activities ensures the quality of the deliverables at that point in the project?
Gate reviewProject milestonesQuality assuranceProject control - Question #50Project Management Concepts
A customer requests an additional requirement for the finished product. After the change is identified and documented, which of the following would be the NEXT step in the process?
Change managementChange control processProject management processImpact assessment - Question #51Project Management Concepts
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organizat...
Stakeholder ManagementChange ManagementRisk ManagementCommunication - Question #52Project Management Concepts
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the s...
Stakeholder feedbackTeam performanceContinuous improvementLessons learned