When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

The correct answer is C. Milestones. Milestones (C) are schedule activities with zero duration that represent a significant event, achievement, or checkpoint in the project - such as 'Design Phase Complete' or 'Regulatory Approval Received.' They do not represent work but serve as markers to track progress…

Project Management Concepts

Question

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options

  • ACritical paths
  • BResources
  • CMilestones
  • DWork breakdown structures

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    93% (26)

Explanation

Milestones (C) are schedule activities with zero duration that represent a significant event, achievement, or checkpoint in the project - such as 'Design Phase Complete' or 'Regulatory Approval Received.' They do not represent work but serve as markers to track progress. Critical paths (A) are sequences of dependent tasks that determine the shortest possible project duration; they consist of activities with actual durations. Resources (B) are people or materials assigned to activities, not activities themselves. A Work Breakdown Structure (D) is a hierarchical decomposition of project scope into deliverables, not a scheduling concept involving zero-duration activities.

Topics

#Milestones#Project scheduling#Schedule activities#Project management terms