A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functiona

Sign in or unlock PK0-005 to reveal the answer and full explanation for question #38. The question stem and answer options stay visible for context.

Project Management Concepts

Question

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Options

  • ADecline because it is not included in the project scope.
  • BAssess the impact of the request and create a change request.
  • CCreate new functional and non-functional requirements for mobile devices.
  • DRevise the baseline of the project plan by adding the new requirements.

Unlock PK0-005 to see the answer

You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Scope Management#Stakeholder Management