nerdexam
CompTIA

PK0-005 · Question #39

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a…

The correct answer is D. A contingency plan. The project manager should have generated a contingency plan first to alleviate the impact of this issue prior to deployment where a major malfunction resulted in an inoperative product condition during a code implementation. A contingency plan is a plan that outlines…

Project Management Concepts

Question

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

Options

  • AA risk budget
  • BA risk impact
  • CA change request
  • DA contingency plan

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    5% (2)
  • C
    11% (5)
  • D
    82% (36)

Explanation

The project manager should have generated a contingency plan first to alleviate the impact of this issue prior to deployment where a major malfunction resulted in an inoperative product condition during a code implementation. A contingency plan is a plan that outlines alternative courses of action or strategies to deal with potential problems or risks that may occur during a project. A contingency plan can help to prevent or minimize the negative impacts of unforeseen events or issues on the project objectives and deliverables and ensure business continuity and stability.

Topics

#Contingency Planning#Risk Management#Project Planning

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice