nerdexam
CompTIACompTIA

PK0-005 · Question #40

PK0-005 Question #40: Real Exam Question with Answer & Explanation

The correct answer is C: Quality assurance. The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and docum

Project Management Concepts

Question

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options

  • AProcurement
  • BCommunication
  • CQuality assurance
  • DRisk

Explanation

The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and documents the standards, criteria, methods, activities, and tools for ensuring and verifying that the quality requirements and expectations of a project are met. A quality assurance plan can help to improve the quality of the project processes and deliverables and prevent or reduce defects or errors.

Topics

#Quality assurance planning#Project scope alignment#Project goals#Project management plans

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions