PK0-005 · Question #40

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the…

The correct answer is C. Quality assurance. The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and…

Project Management Concepts

Question

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options

  • AProcurement
  • BCommunication
  • CQuality assurance
  • DRisk

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    83% (30)
  • D
    11% (4)

Explanation

The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and documents the standards, criteria, methods, activities, and tools for ensuring and verifying that the quality requirements and expectations of a project are met. A quality assurance plan can help to improve the quality of the project processes and deliverables and prevent or reduce defects or errors.

Topics

#Quality assurance planning#Project scope alignment#Project goals#Project management plans