PK0-005 · Question #41

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

The correct answer is C. Review the communication plan. The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency…

Tools and documentation

Question

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

Options

  • AEscalate the communication issues.
  • BImplement a communication platform.
  • CReview the communication plan.
  • DTalk with the head of the PMO.

How the community answered

(60 responses)
  • A
    3% (2)
  • B
    10% (6)
  • C
    82% (49)
  • D
    5% (3)

Explanation

The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.

Topics

#Communication issues#Communication plan#Stakeholder communication#Issue resolution