PK0-005 · Question #36
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
The correct answer is A. Dashboard. A dashboard (A) provides a high-level, visual summary of key project metrics - such as schedule status, budget, risks, and milestones - making it ideal for executive sponsors and senior stakeholders who need a quick, clear picture of project health. A Gantt chart (B) is a…
Question
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
Options
- ADashboard
- BGantt chart
- CWork breakdown structure
- DRequirements Traceability Matrix
How the community answered
(53 responses)- A77% (41)
- B8% (4)
- C4% (2)
- D11% (6)
Explanation
A dashboard (A) provides a high-level, visual summary of key project metrics - such as schedule status, budget, risks, and milestones - making it ideal for executive sponsors and senior stakeholders who need a quick, clear picture of project health. A Gantt chart (B) is a detailed scheduling tool used by the project team to manage tasks and timelines; it is too granular for executive reporting. A Work Breakdown Structure (C) decomposes deliverables hierarchically and is a planning tool, not a status reporting tool. A Requirements Traceability Matrix (D) tracks requirements through the project lifecycle and is not suited for executive progress updates.
Topics