nerdexam
CompTIACompTIA

PK0-005 · Question #31

PK0-005 Question #31: Real Exam Question with Answer & Explanation

The correct answer is C: Update the project charter.. Update the project charter. Updating the project charter would be the next step for the project manager after identifying the project team during the project initiation phase. A project charter is a document that formally authorizes a project and defines its purpose, scope, objec

Project Life Cycle Phases

Question

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options

  • ADetermine budget constraints.
  • BValidate the business case.
  • CUpdate the project charter.
  • DCreate a project schedule.

Explanation

Update the project charter. Updating the project charter would be the next step for the project manager after identifying the project team during the project initiation phase. A project charter is a document that formally authorizes a project and defines its purpose, scope, objectives, deliverables, milestones, roles and responsibilities, assumptions, constraints, risks, budget, and timeline. A project charter can help to align the expectations and interests of all stakeholders involved in a project and provide direction and guidance for planning and executing the project.

Topics

#Project Initiation#Project Charter#Project Manager Responsibilities#Project Phases

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions