PK0-005 · Question #19

PK0-005 Question #19: Real Exam Question with Answer & Explanation

The correct answer is D: Contact the PMO for assistance.. The project manager should contact the project management office (PMO) for assistance after learning that a similarly time-consuming project was executed previously in the organization. A PMO is a department or group within an organization that provides centralized guidance, gove

Project Management Concepts

Question

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time- consuming project was executed previously in the organization. Which of the following actions should the PM take?

Options

  • APerform a root cause analysis.
  • BOrganize a stakeholder meeting.
  • CEscalate the issue to the CCB.
  • DContact the PMO for assistance.

Explanation

The project manager should contact the project management office (PMO) for assistance after learning that a similarly time-consuming project was executed previously in the organization. A PMO is a department or group within an organization that provides centralized guidance, governance, standards, best practices, resources, and oversight for project management activities. A PMO can help the project manager by providing access to historical data, lessons learned, templates, tools, methodologies, and expertise from previous projects that can be useful for planning and executing the current project.

Topics

#PMO functions#Organizational support#Lessons learned#Project issue resolution