PK0-005 · Question #20

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST…

The correct answer is B. A project manager did not release the resources. A project manager did not release the resources. A project manager not releasing the resources could most likely be the cause of this issue where several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project…

Project Management Concepts

Question

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options

  • AA project manager assigned the wrong resources.
  • BA project manager did not release the resources.
  • CA project manager did not remove the system access.
  • DA project manager did not provide the project sign-off.

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    77% (23)
  • C
    13% (4)
  • D
    3% (1)

Explanation

A project manager did not release the resources. A project manager not releasing the resources could most likely be the cause of this issue where several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Releasing resources is a process of freeing up or reallocating any human or material resources that were used for a project after its completion or closure. Releasing resources can help to update the resource availability and utilization records and avoid any conflicts or errors in resource allocation

Topics

#Resource management#Resource allocation#Over-allocation#Project closure