Which of the following requires the MOST availability from the business team?

The correct answer is B. Scrum. Scrum requires the most availability from the business team among the given options. Scrum is a popular agile framework that organizes work into short iterations called sprints, usually lasting one to four weeks. Scrum emphasizes collaboration between teams, customers, and…

Project Management Concepts

Question

Which of the following requires the MOST availability from the business team?

Options

  • ASDLC
  • BScrum
  • CPRINCE2
  • DWaterfall

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    88% (42)
  • C
    2% (1)
  • D
    6% (3)

Explanation

Scrum requires the most availability from the business team among the given options. Scrum is a popular agile framework that organizes work into short iterations called sprints, usually lasting one to four weeks. Scrum emphasizes collaboration between teams, customers, and stakeholders and encourages open communication and transparency throughout the project lifecycle. Scrum requires frequent involvement and feedback from the business team through activities such as product backlog refinement, sprint planning, sprint review, sprint retrospective, and daily scrum meetings.

Topics

#Project Management Methodologies#Agile#Scrum#Stakeholder Engagement