nerdexam
CompTIA

PK0-005 · Question #18

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains…

The correct answer is D. SOW. The client provided a statement of work (SOW) to the project manager and suggested that the project manager and team just need to execute the plan. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW…

Tools and documentation

Question

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

  • Purpose
  • Scope of work
  • Location of work
  • Period of performance
  • Deliverables schedule
  • Applicable standards
  • Acceptance criteria
  • Special requirements
  • Payment schedule

Which of the following documents did the client provide to the project manager?

Options

  • ARFP
  • BWBS
  • CSLA
  • DSOW

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    6% (3)
  • D
    90% (45)

Explanation

The client provided a statement of work (SOW) to the project manager and suggested that the project manager and team just need to execute the plan. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.