Which of the following criteria would favor using the agile methodology to manage an upcoming project?
The correct answer is D. Multiple undefined tasks. One of the best use cases for agile project's is project's that have multiple undefined tasks.
Project Management Concepts
Question
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Options
- AStrong projectized organization
- BMedium risk
- CLack of resources
- DMultiple undefined tasks
How the community answered
(36 responses)- A8% (3)
- B3% (1)
- C3% (1)
- D86% (31)
Explanation
One of the best use cases for agile project's is project's that have multiple undefined tasks.