PK0-005 · Question #17

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

The correct answer is D. Multiple undefined tasks. One of the best use cases for agile project's is project's that have multiple undefined tasks.

Project Management Concepts

Question

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options

  • AStrong projectized organization
  • BMedium risk
  • CLack of resources
  • DMultiple undefined tasks

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    86% (31)

Explanation

One of the best use cases for agile project's is project's that have multiple undefined tasks.

Topics

#Agile Methodology#Project Selection Criteria#Undefined Requirements#Project Characteristics