nerdexam
CompTIA

PK0-005 · Question #1

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete…

The correct answer is B. Communicate the change deployment. The change control process follows a defined sequence: (1) document the request in the change log, (2) conduct an impact assessment, (3) approve or reject the change, (4) implement the change, and (5) communicate the change deployment. In this scenario, the change has already…

Project Management Concepts

Question

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options

  • ADocument the request in the change control log.
  • BCommunicate the change deployment.
  • CConduct an impact assessment.
  • DImplement the change.

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    81% (21)
  • C
    8% (2)
  • D
    4% (1)

Explanation

The change control process follows a defined sequence: (1) document the request in the change log, (2) conduct an impact assessment, (3) approve or reject the change, (4) implement the change, and (5) communicate the change deployment. In this scenario, the change has already been approved and implemented (the project plan was updated with the new end date). The NEXT logical step is to communicate the change deployment to all relevant stakeholders so they are aware of the updated schedule. Documenting the request and conducting the impact assessment occur before implementation, not after.

Topics

#Change Management#Project Communication#Project Plan Update#Change Control Process

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice