nerdexam
CompTIA

PK0-005 · Question #8

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

The correct answer is C. Task board. A task board (also known as a Kanban board or Scrum board) visually represents work items in columns such as 'To Do,' 'In Progress,' and 'Done.' It is the standard tool used during daily stand-up meetings (a common Agile ceremony) to track team progress on tasks. A decision…

Tools and documentation

Question

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options

  • ADecision board
  • BWhiteboard
  • CTask board
  • DDashboard

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    86% (30)
  • D
    3% (1)

Explanation

A task board (also known as a Kanban board or Scrum board) visually represents work items in columns such as 'To Do,' 'In Progress,' and 'Done.' It is the standard tool used during daily stand-up meetings (a common Agile ceremony) to track team progress on tasks. A decision board (A) is used to capture and track decisions. A whiteboard (B) is a general-purpose tool, not a specific project artifact. A dashboard (D) provides high-level KPIs and metrics across multiple areas, not specifically task-level progress for stand-ups.

Topics

#Task boards#Agile methodologies#Progress tracking#Stand-up meetings

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice