PK0-005 · Question #7
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
The correct answer is A. Gantt chart. A Gantt chart is a scheduling tool that visually displays project tasks against a timeline, showing planned versus actual progress, task durations, dependencies, and milestones. When a sponsor raises concerns about the project timeline, a Gantt chart is the most appropriate…
Question
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
Options
- AGantt chart
- BMaintenance window schedule
- CFunctional requirements
- DTest results
How the community answered
(43 responses)- A79% (34)
- B12% (5)
- C7% (3)
- D2% (1)
Explanation
A Gantt chart is a scheduling tool that visually displays project tasks against a timeline, showing planned versus actual progress, task durations, dependencies, and milestones. When a sponsor raises concerns about the project timeline, a Gantt chart is the most appropriate tool to review the schedule, identify delays, and show the project's current status against the original plan. A maintenance window schedule (B) is for IT operations. Functional requirements (C) define what the project should deliver. Test results (D) indicate quality, not schedule performance.
Topics
Community Discussion
No community discussion yet for this question.