PK0-005 · Question #6
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Choose two.)
The correct answer is A. Company vision D. Mission statement. When prioritizing a project portfolio based on a company's strategic plan, the program manager must evaluate alignment with the organization's core strategic documents. The company vision (A) defines the long-term aspirational direction of the organization, and the mission…
Question
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Choose two.)
Options
- ACompany vision
- BGlobal environment
- CBrand value
- DMission statement
- EPortfolio budget
- FLocal legislation
How the community answered
(33 responses)- A91% (30)
- E6% (2)
- F3% (1)
Explanation
When prioritizing a project portfolio based on a company's strategic plan, the program manager must evaluate alignment with the organization's core strategic documents. The company vision (A) defines the long-term aspirational direction of the organization, and the mission statement (D) articulates its fundamental purpose - both are the primary drivers of strategic alignment. Brand value, global environment, local legislation, and portfolio budget are operational or contextual factors that may influence execution, but they are not the foundational strategic documents used to evaluate whether a project aligns with the company's strategic plan.