PK0-005 · Question #5

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Choose two.)

The correct answer is E. Review the resource pool. F. Review the project objectives. When a project manager is first assigned to a new project, before developing any plans or scope, they must first understand the foundational context: reviewing the resource pool (E) reveals what human and material resources are available to accomplish work, and reviewing the…

Project Life Cycle Phases

Question

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Choose two.)

Options

  • AReview the detailed plan.
  • BDevelop a preliminary scope.
  • CDevelop a transition plan.
  • DDevelop a project management plan.
  • EReview the resource pool.
  • FReview the project objectives.

How the community answered

(35 responses)
  • B
    3% (1)
  • D
    3% (1)
  • E
    94% (33)

Explanation

When a project manager is first assigned to a new project, before developing any plans or scope, they must first understand the foundational context: reviewing the resource pool (E) reveals what human and material resources are available to accomplish work, and reviewing the project objectives (F) ensures the PM understands what the project is trying to achieve. Developing a project management plan, preliminary scope, and detailed plan all come later in the planning phase. Reviewing project objectives and available resources are the earliest orientation activities that inform all subsequent planning decisions.

Topics

#Project initiation#Project manager responsibilities#Project objectives#Resource assessment