PK0-005 · Question #12

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

The correct answer is D. Develop a rollback plan. In the operational infrastructure change process, after the maintenance window has been determined, the NEXT step is to develop a rollback plan before making any notifications or executing the change. A rollback plan defines the steps to revert the system to its previous state…

Project Management Concepts

Question

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Options

  • AImplement the change.
  • BApprove the test plan.
  • CNotify customers.
  • DDevelop a rollback plan.

How the community answered

(28 responses)
  • A
    4% (1)
  • C
    4% (1)
  • D
    93% (26)

Explanation

In the operational infrastructure change process, after the maintenance window has been determined, the NEXT step is to develop a rollback plan before making any notifications or executing the change. A rollback plan defines the steps to revert the system to its previous state if the change causes unexpected problems. It must be prepared and validated before customers are notified or the change is implemented, so that if something goes wrong during the change window, the team can recover quickly and minimize downtime. Notifying customers and implementing the change come after the rollback plan is in place.

Topics

#Change Management Process#Rollback Planning#Operational Changes#Risk Mitigation