PK0-005 · Question #12
PK0-005 Question #12: Real Exam Question with Answer & Explanation
The correct answer is D: Develop a rollback plan.. The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure
Question
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
Options
- AImplement the change.
- BApprove the test plan.
- CNotify customers.
- DDevelop a rollback plan.
Explanation
The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact and risk of the change and ensure business continuity and stability.
Topics
Community Discussion
No community discussion yet for this question.