PK0-005 · Question #24
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
The correct answer is C. Statement of work. Once the need to procure goods and/or services is identified, the next document a project manager should update is the Statement of Work (SOW). The SOW is a formal document that defines the project's specific deliverables, requirements, and timeline, and it serves as a guide…
Question
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
Options
- AMemorandum of understanding
- BRequest for information
- CStatement of work
- DNon-disclosure agreement
How the community answered
(32 responses)- A3% (1)
- B6% (2)
- C81% (26)
- D9% (3)
Explanation
Once the need to procure goods and/or services is identified, the next document a project manager should update is the Statement of Work (SOW). The SOW is a formal document that defines the project's specific deliverables, requirements, and timeline, and it serves as a guide for the supplier or vendor during the procurement process. The SOW helps to establish a clear understanding between the project team and the supplier/vendor regarding the scope and expectations of the goods/services to be procured.
Topics
Community Discussion
No community discussion yet for this question.