For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

The correct answer is D. RACI chart. A RACI chart (D) is the most useful tool for illustrating who holds which role (Responsible, Accountable, Consulted, Informed) across major project activities - exactly what a kickoff audience needs to understand. A resource plan (A) shows what resources are allocated but does…

Tools and documentation

Question

For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options

  • AResource plan
  • BOrganizational chart
  • CProject charter
  • DRACI chart

How the community answered

(63 responses)
  • A
    14% (9)
  • B
    8% (5)
  • C
    3% (2)
  • D
    75% (47)

Explanation

A RACI chart (D) is the most useful tool for illustrating who holds which role (Responsible, Accountable, Consulted, Informed) across major project activities - exactly what a kickoff audience needs to understand. A resource plan (A) shows what resources are allocated but does not map roles to specific activities. An organizational chart (B) shows reporting hierarchy, not activity-level role assignments. A project charter (C) is a high-level authorization document that outlines goals, scope, and stakeholders - it does not provide the activity-role mapping needed at a kickoff.

Topics

#RACI chart#Roles and responsibilities#Project planning tools#Project documentation