For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
The correct answer is D. RACI chart. A RACI chart (D) is the most useful tool for illustrating who holds which role (Responsible, Accountable, Consulted, Informed) across major project activities - exactly what a kickoff audience needs to understand. A resource plan (A) shows what resources are allocated but does…
Question
For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
Options
- AResource plan
- BOrganizational chart
- CProject charter
- DRACI chart
How the community answered
(63 responses)- A14% (9)
- B8% (5)
- C3% (2)
- D75% (47)
Explanation
A RACI chart (D) is the most useful tool for illustrating who holds which role (Responsible, Accountable, Consulted, Informed) across major project activities - exactly what a kickoff audience needs to understand. A resource plan (A) shows what resources are allocated but does not map roles to specific activities. An organizational chart (B) shows reporting hierarchy, not activity-level role assignments. A project charter (C) is a high-level authorization document that outlines goals, scope, and stakeholders - it does not provide the activity-role mapping needed at a kickoff.