PMI-SP Exam Questions
328 real PMI-SP exam questions with expert-verified answers and explanations. Page 6 of 7.
- Question #267
Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure...
- Question #268
You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeh...
- Question #269
Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtu...
- Question #270
You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to...
- Question #271
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and dis...
- Question #272
Mark works as a project manager for BlueWell Inc. He is making relevant information available to the project stakeholders as required. According to Mark, which of the following are...
- Question #273
Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually...
- Question #274
You are the project manager of the NHQ Project. Management has told you that resource leveling will be enforced on your project, but they still want you to complete the project by...
- Question #275
You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance i...
- Question #276
Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
- Question #277
What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?
- Question #278
You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the cri...
- Question #280
Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project h...
- Question #281
Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are...
- Question #282
You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the criti...
- Question #283
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know wha...
- Question #284
Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? E...
- Question #285
What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and managem...
- Question #286
A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Ch...
- Question #287
Which of the following is NOT an output of the control schedule process?
- Question #288
You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than schedu...
- Question #289
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project,...
- Question #290
You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, w...
- Question #291
Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers...
- Question #292
Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and c...
- Question #293
You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The activity list is based on the work packages defined in the project's WBS. Ac...
- Question #294
Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of pro...
- Question #295
You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule d...
- Question #296
Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member,...
- Question #297
Which of the following provides a method to track project progress during project execution against what was planned?
- Question #298
You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You ar...
- Question #299
Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the w...
- Question #300
What project management plan will document the time frame and frequency for the distribution of required information?
- Question #302
Examine the figure given below. In this project network diagram, what is the total float for Activity I?
- Question #304
Once the project's WBS has been created what process may happen next?
- Question #305
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
- Question #306
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication...
- Question #307
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stak...
- Question #308
The Define Activities process is the first process in the project time management knowledge are
- Question #309
Examine the figure given below: If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
- Question #310
You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a mil...
- Question #311
You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will beco...
- Question #312
George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. Th...
- Question #313
Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what...
- Question #314
Examine the figure given below: Which path is considered the critical path?
- Question #315
Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to gene...
- Question #316
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete t...
- Question #317
John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project...
- Question #318
Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.
- Question #319
Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the...