Question
You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?
Options
- AActivity attributes
- BProject management plan
- CSchedule Management Plan
- DRoles and Responsibilities Matrix
Unlock PMI-SP to see the answer