PMI-SP · Question #305
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
The correct answer is A. Precedence Diagramming Method. The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach Answer option C is incorrect. Dependency determination identifies the order of the project work. Answer…
Question
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Options
- APrecedence Diagramming Method
- BSchedule network template
- CDependency determination
- DActivity on the Node
How the community answered
(56 responses)- A88% (49)
- B7% (4)
- C2% (1)
- D4% (2)
Explanation
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach Answer option C is incorrect. Dependency determination identifies the order of the project work. Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram. Answer option D is incorrect. Activity on the node places activities on circles within a network diagram. It is an example of the precedence diagramming method.
Topics
Community Discussion
No community discussion yet for this question.