Once the project's WBS has been created what process may happen next?
The correct answer is B. Define activities. The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Answer option D is incorrect. Sequencing the activities cannot…
Question
Once the project's WBS has been created what process may happen next?
Options
- AEstimate activity resources
- BDefine activities
- CEstimate activity durations
- DSequence activities
How the community answered
(52 responses)- A2% (1)
- B90% (47)
- C2% (1)
- D6% (3)
Explanation
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid. Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.