PMI
PMI-SP · Question #285
PMI-SP Question #285: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #285. The question stem and answer options stay visible for context.
Question
What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project's schedule performance index?
Options
- A($450,000 - $180,000) / ($450,000 - $191,000)
- B$450,000 - $477,500
- C$180,000 / $247,500
- D$180,000 - $247,500
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.