nerdexam
PMI

PMI-SP · Question #285

What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know yo

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #285. The question stem and answer options stay visible for context.

Schedule Monitoring and Controlling

Question

What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project's schedule performance index?

Options

  • A($450,000 - $180,000) / ($450,000 - $191,000)
  • B$450,000 - $477,500
  • C$180,000 / $247,500
  • D$180,000 - $247,500

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#schedule performance index#earned value management#SPI formula#schedule analysis
Full PMI-SP Practice